§ 8-714. Landscaping and grading prior to completion.  


Latest version.
  • When construction work to a residential building or structure is not completed within 14 months, and the exterior work is substantially completed, the Director of Community Development may require that the premises be properly graded and that sod be laid by a date certain, not less than 14 days following written notice to the permittee, provided however, that if the 14-month period would expire during a time when weather conditions prevent sodding, the Director may extend the time required for compliance until such time as it is reasonably practical to do so. Grading shall be done in accordance with an approved Site Grading Plan.

(Code 1993, § 9-13.4; Ord. No. 2001-O-59, 9-11-2001)