§ 24-273. General Permit Application requirements.  


Latest version.
  • (a)

    Minimum processing period. A complete permit application must be filed with the Department of Community Development at least ten business days, excluding holidays, prior to the proposed start of film production. No applications will be accepted for processing that are received less than the required ten business days or, that fail to include all attachments required by this section.

    (b)

    Information required. No permit application shall be deemed complete unless and until the following has been submitted:

    (1)

    $75.00 non-refundable application processing fee;

    (2)

    Signed and notarized permit application form; and

    (3)

    All permit application documentation required by section 24-275, including:

    a.

    Certificate of insurance.

    b.

    Indemnification and hold harmless agreement.

    c.

    Neighbor notification certification.

    d.

    Property owner approval form.

(Code 1993, § 5-8.4; Ord. No. 2007-O-55, 8-28-2007; Ord. No. 2009-O-84, 12-8-2009)